Michigan Energy Files · Calendar

Meeting calendar

Every dated event in the Energy Files’ project data: meetings a public body has scheduled, actions taken by township, county and state bodies and by applicants, and the dates records were captured. Each one links to the record that dates it.

  • Checked:
  • 28 dated events
  • 1 upcoming
  • 16 projects

Upcoming

  1. 7 p.m. ET

    Scheduled Gustin Solar · Harrisville Township

    Harrisville Twp. Planning Commission meets, 7 p.m.

    Harrisville Township’s Planning Commission is scheduled to meet.

    Place: Harrisville Township Hall (unless otherwise posted)

    Checked against the township’s published schedule on Oct 3, 2026; no agenda posted as of then.

    Not verified: No agenda or notice for the Oct 7, 2026 Harrisville meeting had been posted as of Oct 3, 2026; the date comes from the township’s published schedule.

Calendar feed

One file with every entry on this page (17). Subscribe and your calendar app checks it for changes; or download it once.

Subscribe in a calendar app

Download the feed (.ics)

To subscribe by address, paste https://insidemichigan.org/projects/calendar/insidemichigan.ics into your calendar’s “add by URL”.

How to read this calendar

How to read this. Scheduled is a date a public body has published for a meeting; it does not say what will be on the agenda. Action is something a body or an applicant did, on the date a record gives. As listed is what a public list showed on the day it was captured; the MPSC siting table carries no filing or decision dates.

Times are Michigan (Eastern) time. An event with no time is dated by its record to the day only.

Filter by project

Past events

October 2026 (2)

  1. As listed Data capture, not a meeting

    Status of 12 projects captured from the MPSC siting table

    Not verified: No filing or decision dates are in the MPSC table; the only dated record is the Oct 1, 2026 capture.

    The 12 projects and their listed status
    • Acceleration Solar: MPSC table lists the case as “Certificate Granted” · row U-21932
    • Birch Valley Solar: MPSC table lists the case as “Schedule suspended; Case paused” · row U-22072
    • Fiddlehead Solar: MPSC table lists the case as “Incomplete Application” · row U-22041
    • Glacier Meadows Solar: MPSC table lists the case as “Under Review, Complete Application” · row U-22044
    • Headland Solar: MPSC table lists the case as “Under Review, Complete Application” · row U-22004
    • Lakeside Solar: MPSC table lists the case as “Incomplete Application” · row U-22143
    • Otisville Solar: MPSC table lists the case as “Under Review, Complete Application” · row U-21956
    • Riverbend Wind: MPSC table lists the case as “Under Review, Complete Application” · row U-22036
    • Rouget Road Solar: MPSC table lists the case as “Under Review” · row U-22003
    • Silver Maple Solar: MPSC table lists the case as “Under Review” · row U-22071
    • Walker Road Solar: MPSC table lists the case as “Application withdrawn” · row U-22130
    • Washtenaw Solar Energy: MPSC table lists the case as “Under Review, Complete Application” · row U-21962
  2. As listed Munro Solar

    Listed on the site’s projects page; no primary record mirrored

    Munro Solar was listed on the site’s projects page with no primary record mirrored.

September 2026 (1)

  1. Action Caledonia Solar

    Township board approved Ordinance 26-01

    Caledonia Township’s board approved Ordinance 26-01.

    Not verified: The Sept 8, 2026 board minutes do not say that Ordinance 26-01 is the amendment heard on Aug 31.

August 2026 (6)

  1. Action Caledonia Solar

    Hearing held; zoning changes approved and sent to the county

    Caledonia Township’s Planning Commission held its hearing and approved zoning ordinance changes; its minutes say no solar application has been submitted.

  2. Action Acceleration Solar

    MPSC approved the settlement agreement

    The MPSC approved a settlement agreement permitting Acceleration Solar, 90 MW, in Ingham County.

  3. Action Logan Solar

    Ogemaw County Board adopted Resolution 26-134 (one-year moratorium)

    Ogemaw County’s Board of Commissioners adopted a one-year moratorium on new solar, wind, battery-storage and data-center applications.

  4. Action Logan Solar

    Ogemaw County Planning Commission hearing on Text Amendment 01-26

    Ogemaw County’s Planning Commission held a public hearing and recommended a zoning text amendment setting a temporary moratorium.

  5. Action Caledonia Solar

    Caledonia Twp. Planning Commission set an Aug 31 hearing on zoning amendments

    Caledonia Township’s Planning Commission set an Aug 31 public hearing on zoning ordinance amendments.

  6. Action Gustin Solar · Gustin Township

    Gustin Twp. Planning Commission denied the 25 MW addition, 5–0

    Gustin Township’s Planning Commission denied a 25 MW addition to Gustin Solar; its 2024 approval of 215 MW has not been rescinded in any record we found.

July 2026 (2)

  1. Action Acceleration Solar

    Settlement agreement filed

    The parties in the Acceleration Solar case filed a settlement agreement for the Commission to consider.

  2. Action Gustin Solar · Gustin Township

    Gustin Twp. hearing: motion to approve tabled

    At Gustin Township’s hearing on the 25 MW addition, a motion to approve with conditions was made and then tabled.

    Not verified: The Dec 2, 2024 and July 13, 2026 minutes are scans; their quotes were checked against OCR text.

June 2026 (1)

  1. Action Gustin Solar · Harrisville Township

    Application submitted to Harrisville Twp. (letter dated June 15, 2026)

    Consumers Energy submitted a special land use application to Harrisville Township for its 94 MW part of Gustin Solar.

May 2026 (1)

  1. Action Gustin Solar · Gustin Township

    Application for a 25 MW addition (dated May 15, 2026)

    Consumers Energy’s application to Gustin Township for a 25 MW addition is dated May 15, 2026.

September 2025 (1)

  1. Action Gustin Solar

    Consumers Energy announced Gustin Solar (335 MW)

    Consumers Energy announced Gustin Solar, 335 MW across Gustin and Harrisville Townships.

    Not verified: The Sept 26, 2025 announcement is taken from the site’s briefing; Consumers Energy’s release is not in the mirror.

June 2025 (1)

  1. Action Acceleration Solar

    Application filed with the MPSC

    Acceleration Solar filed an application with the MPSC for a 90 MW solar project in Ingham County.

December 2024 (1)

  1. Action Gustin Solar · Gustin Township

    Gustin Twp. Planning Commission approved 215 MW (Sapling Solar)

    Gustin Township’s Planning Commission granted special land use approval for the 215 MW Sapling Solar project, later part of Gustin Solar.

    Not verified: The Dec 2, 2024 and July 13, 2026 minutes are scans; their quotes were checked against OCR text.

By project

Each project’s dated events, oldest first. Each links to its entry above.

Acceleration Solar (4)

  1. Application filed with the MPSC
  2. Settlement agreement filed
  3. MPSC approved the settlement agreement
  4. MPSC table lists the case as “Certificate Granted”

Birch Valley Solar (1)

  1. MPSC table lists the case as “Schedule suspended; Case paused”

Caledonia Solar (3)

  1. Caledonia Twp. Planning Commission set an Aug 31 hearing on zoning amendments
  2. Hearing held; zoning changes approved and sent to the county
  3. Township board approved Ordinance 26-01

Fiddlehead Solar (1)

  1. MPSC table lists the case as “Incomplete Application”

Glacier Meadows Solar (1)

  1. MPSC table lists the case as “Under Review, Complete Application”

Gustin Solar (7)

  1. Gustin Twp. Planning Commission approved 215 MW (Sapling Solar)
  2. Consumers Energy announced Gustin Solar (335 MW)
  3. Application for a 25 MW addition (dated May 15, 2026)
  4. Application submitted to Harrisville Twp. (letter dated June 15, 2026)
  5. Gustin Twp. hearing: motion to approve tabled
  6. Gustin Twp. Planning Commission denied the 25 MW addition, 5–0
  7. Harrisville Twp. Planning Commission meets, 7 p.m.

Headland Solar (1)

  1. MPSC table lists the case as “Under Review, Complete Application”

Lakeside Solar (1)

  1. MPSC table lists the case as “Incomplete Application”

Logan Solar (2)

  1. Ogemaw County Planning Commission hearing on Text Amendment 01-26
  2. Ogemaw County Board adopted Resolution 26-134 (one-year moratorium)

Munro Solar (1)

  1. Listed on the site’s projects page; no primary record mirrored

Otisville Solar (1)

  1. MPSC table lists the case as “Under Review, Complete Application”

Riverbend Wind (1)

  1. MPSC table lists the case as “Under Review, Complete Application”

Rouget Road Solar (1)

  1. MPSC table lists the case as “Under Review”

Silver Maple Solar (1)

  1. MPSC table lists the case as “Under Review”

Walker Road Solar (1)

  1. MPSC table lists the case as “Application withdrawn”

Washtenaw Solar Energy (1)

  1. MPSC table lists the case as “Under Review, Complete Application”

Where this comes from

Nothing on this page is entered by hand. Every event is taken from the project file behind the tracker (compiled Oct 1, 2026) and keeps that file’s own label, summary and record. The same events are published as data in events.json and as the calendar feed above. Records are hosted verbatim in the records library.